You are here

Construction Activities

Projects for The Ohio State University Airport

 

April 2019 - December 2019

Corporate Airpark Development 

The first phase construction of the new corporate airpark is underway.

Site preparation for the first new corporate hangar began mid-April and is nearing completion. Hangar construction is scheduled to begin the latter half of May, with occupancy at year's end.

While the hangar is being constructed,  a new entrance drive from West Case Road and a taxilane connector to taxiway A will be constructed as well.

New hangar site preparation

 

July 2019:  Phase 2 - Runway 9L/27R Rehabilitation

This project will complete the rehabilitation by finishing both ends of the runway,

micro-surfacing Taxiway G, and a "mill-and-fill" asphalt course on Taxiway F.

Estimated start time: July 8th

Duration: 8 weeks